Print this page
Friday, 31 October 2014 08:39

Construction work almost halved on Yorkshire Water reservoir upgrade

Innovative cost-saving solutions have played a key role in the upgrade of Yorkshire Water’s Doe Park Reservoir, almost halving construction time on the scheme.

Impounded behind a Victorian Pennine-style embankment dam, work of this magnitude at the 800,000m3 reservoir near Denholme would usually take up to 12 months. However, by implementing techniques and specifications from pre-cast concrete specialist Whites Concrete, construction time was almost halved to just over six months.

1 Doe Park Reservoir during its upgradeInstead of traditional masonry, the exposed external concrete faces of the wave wall and spillway were covered with masonry-effect formliner. This more sustainable option has also saved £70,000 initially.

Main elements of the scheme included:

  • Design & reconstruction of dam crest to ensure the flood rise from the PMF was fully contained.
  • Design and construction of a 17m single-span bridge over the spillway channel (for HA loading).
  • Design and construction of a new concrete spillway channel capable of passing the design flood of 120m3/s.
  • Improvements to the existing valve shaft and access bridge so that the shaft does not act as an overflow during the PMF.

During construction of the spillway, pre-fabricated reinforcement saved considerable time and also improved safety because it minimised the amount of steel fixing required on site.

A further 12 weeks were also saved by using pre-cast concrete wave wall units, compared to in-situ concrete and shuttering.  This accelerated option also helped maintain much needed access to a property on the other side of the dam.

As part of collaborative planning and lean construction techniques, treated recycled sludge was used instead of topsoil, which saved a further £14,000.

Visit www.whitesconcrete.co.uk