NI Water progresses £18m Ards North Wastewater Improvement Project

A new pipeline due to be laid in Ballywalter at the end of July will form an integral part of an extensive programme of work planned by NI Water to upgrade local wastewater systems to bring about social, economic and environmental benefits.

NI_Water_Ards_peninsula_1.jpg

Ards peninsula

The £18 million Ards North Wastewater Improvement Project, which has recently got underway, will rationalise and improve the wastewater collection, treatment and transfer systems serving the Carrowdore, Ballywhiskin and Ballywalter areas.

At the heart of the two-year programme of work is the construction of a modern new wastewater treatment works (WwTW) on a greenfield site off the Ganaway Road in Ballywalter.

A number of new pumping stations will also be constructed as part of the project, and new pipelines laid to transfer all wastewater flows from the Carrowdore, Ballywhiskin and Ballywalter areas, as well as those from nearby caravan parks, to the new Ards North WwTW.

The state-of-the art facility will treat the wastewater to a high standard before discharging the clean effluent out to sea via a new long sea outfall which will be constructed 3 metres below the seabed off the coast at Ballyferris.

Commenting on the substantial programme of work, Damien McKeown, NI Water’s Project Manager said:

“Site clearance works have recently got underway at the Ganaway Road site in preparation for construction of the new WwTW and plans are now in place to commence the extensive network improvements that are included within the project.

“The network improvements will commence in Ballywalter with a new pumping main being laid between Ballywalter Wastewater Pumping Station (located at Fowler Way) and the new Ards North WwTW. From Fowler Way, the route of this pumping main will go along Main Street, Broadway and Whitechurch Road up to its junction with the Greystone Road.

The works are being carried out by BSG Civil Engineering on behalf of NI Water. The contractor will undertake the pipelaying work by directional drilling where possible in order to minimise disruption. Use of the trenchless technology means that only pits need to be dug at certain intervals along the pipeline route which helps to reduce the amount of excavation required.