Wed, Oct 22, 2025
Text Size
Thursday, 12 November 2020 11:54

United Utilities completes first major milestone of £1bn AMP7 Haweswater Aqueduct Resilience Programme

United Utilities has completed the first major milestone of the £1 billion Haweswater Aqueduct Resilience Programme – on time, in a storm and despite COVID.

UU North connection 4 pipes 1

A team of 180 specialist engineers achieved the impressive feat of engineering in the North West near Kendal despite severe storms and the effects of the COVID pandemic.

United Utilities connected four new 1.6m diameter pipes into the Haweswater Aqueduct – the huge underground structure supplying a third of the North West’s water- in under eight days.

Connecting the brand new section near Hallbank meant shutting down the aqueduct for the shortest period possible and marked its first major repair in the 65 years since it was built.

The impressive feat of engineering completed at Hallbank is the first milestone in a much bigger project which will see the replacement of six more tunnel sections along the 109km Haweswater Aqueduct which supplies drinking water to 2.5 million customers in Cumbria, Lancashire and Greater Manchester.

UU North connection complete 1

Project Director John Hilton said every hour of every day had been planned in meticulous detail to make sure it went smoothly.

“This is only the third time in its life that the aqueduct has ever been drained and I’ve been there every time. You’d think it would get easier but it doesn’t. This time we were working during a pandemic and we had biblical rain like you wouldn’t believe. When you’re planning something on this scale it’s right to be sensibly paranoid,” he said.

After nearly two years constructing the new 2.5km section of pipe, United Utilities handed the entire site to framework contractor Mott Macdonald Bentley to complete the connections. At its peak 90 engineers on round-the-clock socially-distanced shifts were working at either end.

The site was handed back to United Utilities early, after just seven days 22 hours and 46 minutes.

In the final hours, storms were so fierce that large steel huts erected to shelter welding activities were left in place to provide weather protection for the remaining work.

John Hilton - UU 1John Hilton continued:

“The other big issue we faced was COVID. As well as rigorous round-the-clock cleaning, team distancing and testing, almost 100 extra trained staff had to be put on stand-by in case an entire work team had to self-isolate. We had hot and cold food brought in and we took over two hotels- one for the night shift, one for the day shift, to reduce the risk of contamination.”

A dedicated team of cleaners worked 24 hours at each end of the pipe constantly disinfecting equipment and work areas.

Project sponsor Martin Padley added:

“Despite the weather, this is the best time of year because there’s plenty of water available from other sources.”

“The main thing is that we have safeguarded a major essential piece of our regional water network for future generations and none of our customers were any the wiser. It takes careful planning, and round the clock vigilance by our teams across the region, to keep everyone’s taps flowing.

“United Utilities has a world class reputation for this kind of high intensity work. We shut the entire pipeline for two weeks in 2013 for its first ever complete inspection. After detailed analysis, and a further inspection in 2016, engineers identified several places where they needed to do some maintenance. This section at Hallbank is the first one.”

No time was wasted while the pipeline was out of operation - another team of engineers took the opportunity to enter the Haweswater Aqueduct further south to carry out more inspection work.

Plans for the Haweswater Aqueduct Resilience Programme are still in development with work on this mammoth £1 billion pipe refurbishment project proposed to begin in 2023.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more