Mon, Apr 27, 2026
Text Size
Friday, 24 April 2020 07:01

Environment Agency continues work on £45m flood defence scheme for York

Work is continuing on the Environment Agency;s £45 million flood alleviation scheme for York to better protect properties in the city from the effects of flooding.

Flood gate - York flood defence scheme

One of the new flood gates at North Street working in recent flooding in York

However, the Agency said in light of the Coronavirus situation and Government advice it is cancelling all public meetings until it is safe to hold them again.

Ben Hughes, project director of the scheme, said:

“We are doing all we can to ensure work continues as much as is feasible, and that delays caused by the knock-on effects of this pandemic are kept to an absolute minimum.”

“Our priority in these difficult times is the health, safety and wellbeing of residents and staff, so we have closed our drop-in hub on Wellington Row and we will not be holding any public engagement events.”

The Agency recently completed work to raise the height of the North Street flood defence, which successfully handled its first test when the city suffered flooding earlier this year. The work saw new flood gates installed, including a new wider gate to allow better flow for pedestrians into North Street gardens.

Ben Hughes continued:

“This February was the wettest since records began, with peak river levels at the Viking recorder reaching 4.47m. During this time the gates and wall did their job.

“To complete this flood cell and increase the level of protection to properties in this area we still need to replace the floodgate under Lendal arch which is programmed for this September.”

Work is also due to continue on raising the embankment between Water End bridge and Scarborough Bridge, behind St Peter’s School.

Local authority planning committees are separately considering proposals for two of the flood ‘cells’ that make up the wider York flood alleviation scheme – the Clementhorpe and the Foss flood storage areas.

Plans for the Clementhorpe scheme, which will better protect 135 homes, include a floodgate as well as flood defence walls.

The Foss flood storage area would be built north of Strensall on the River Foss. It would hold back water and slow the flow back into the city in times of heavy rainfall.

Along with the upgraded Foss Barrier, this would better protect more than 1,000 properties along the Foss corridor, such as Huntington Road.

Due to the flood storage area straddling two local authorities, the planning application is being heard by both Ryedale District Council and City of York Council.

A planning application has also been submitted for flood defence work at Bishopthorpe.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more