Work is set to begin on the Environment Agency’s £19.8 million scheme to protect Torcross from further storm damage, after devastating storms in January and February 2026.

Storm impacts at Torcross from early 2026. Photo: Forest and Beach
The scheme will see almost 90,000 tons of new rock armour placed on the shoreline frontage to better protect the Torcross community by reducing energy from the waves hitting the shore. In addition, it will also reinstate damaged defences at the car park and extend the slipway.
The project has now secured all necessary consents and licences from the Marine Management Organisation and the Local Planning Authority, following consultation with key stakeholders including Natural England.
The first rock delivery by barge is expected next week, subject to weather conditions. Just under 60,000 tonnes of rock will arrive by sea and a further 30,000 tonnes of smaller material will be transported by road.
George Arnison, Environment Agency project lead, said:
“We’re really pleased to have got to this critical point where we have the green light to start construction. I’d like to acknowledge the huge amount of work that’s gone into getting the project to this stage so quickly, much of which is invisible to the public. “
The project will be progressed at an accelerated pace with Kier Infrastructure appointed to deliver the vital engineering works.
Philip Ramsay, operations director, Kier Infrastructure, said:
“The collaborative effort has ensured that we can now start construction in October.
“Our teams will continue to work closely with the Environment Agency and local community to deliver a successful outcome that will protect Torcross for generations to come.”
All rock shipments are scheduled between mid-October and early December 2026, with road deliveries continuing to the end of January 2027.
Rock armour installation will happen between October 2026 and April 2027, with the slipway extension and car park sheet piling in spring 2027. The project is expected to complete, in early summer.
The dates are indicative and may be subject to change due to weather and operational factors.
The £19.8 million funding has been secured from within the Environment Agency’s existing Investment Programme budget, provided by Government through Defra. It is ring-fenced for flood and coastal defence and is separate from any funding related to the A379 road, which falls under the responsibility of Devon County Council as the Highways Authority.
WaterBriefing is supporting the upcoming Floodex & National Drainage Show which takes place in London on 25– 26 November 2026 in London. Now in its eleventh year, Floodex will run alongside the National Civils Show. Between them the events are set to welcome thousands of civil engineers, contractors, developers and planners, involved in construction, utilities, highways, railway and coastal defence professionals.
Click here for more information and to register for your free ticket to attend Floodex/National Drainage Show/Waterways Management
Click here to register for your free ticket to attend the National Civils Show
Near-real-time microbial monitoring of wastewater discharge and bathing waters is now possible thanks to the BactoSense ID solution created by Swiss-based bNovate Technologies.
Craig Nienaber, Business Development Manager for Safe Access Solutions (SAS) at HUBER Technology, explores why the company is seeing a growing level of interest in its safe access solutions for critical infrastructure providers, including their application in wastewater treatment assets.

Southern Water has released film and images showing what it’s like to walk inside Hampshire’s expanded Yew Hill underground reservoir for the very last time, before it gets filled with water.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.