Ofwat has said that of the £655 million requested by Thames for its activities on the Thames Tideway Tunnel, it has only adequately justified £324 million of expenditure.
Thames Water’s AMP6 business plan included £655 million for its activities on the Thames Tideway Tunnel (TTT) in AMP6 (2015-20) in order to:
- deliver an infrastructure provider (IP);
- carry out enabling and interface works for the project; and
- comply with the outcome of the project’s development consent order and also to manage uncertainty around the timing of the appointment of an IP.
However, Ofwat’s current view is that the assessment criteria have not been fully passed.
At an overall project level, the regulator says it recognises the need for the activities Thames expects to carry out between 2015 and 2020. However, at an individual cost component level Thames has not sufficiently justified some areas of its plan in terms of Ofwat’s four cost assessment categories of need, value for money for customers, efficient cost and customer protection.
In terms of robustness of cost estimates, Ofwat says that of the £655 million requested by Thames for its activities on the TTT, it assesses it has only adequately justified £324 million of expenditure.
However, of the total £331m gap, 65% relates to only two challenges, which Ofwat said should be resolvable with further information from Thames. They are in relation to expenditure to keep the overall TTT project to timetable if the appointment of the IP is delayed until October 2015 and Thames’ approach to its risk estimate.
On delay to the appointment of the IP, Thames has requested £110 million to carry out additional activities it would need to undertake should the appointment of the IP be delayed until October 2015. However, it did not commit to what activities it needed to carry out. Ofwat said that while it understands the need for additional costs under this scenario (some of which would otherwise be incurred by the IP, it will not include any costs until Thames commits to what activities it intends to do and provides a robust cost estimate for the work.
Thames has included £136 million for risk in its cost estimate - arrived at by allocating risk from the total risk estimate for the project in AMP6. However, Ofwat said it has done this without any reference to the activities it will carry out in AMP6 and without considering how this overlaps with its proposed treatment of uncertainty in AMP6. Ofwat has challenged Thames on its approach and not included £106 million in its view of efficient costs.
The rest of the cost challenge1 (£-115 million) relates to:
- inflation;
- construction;
- land-related activities; and
- indirect costs
Ofwat’s challenge to these cost items relates mainly to evidence of efficient costs. Within the land related activities and indirect cost categories, the regulator said there was also insufficient evidence to demonstrate need for the expenditure requested.
Ofwat stated:
“Based on the information provided to us by Thames so far, there is insufficient evidence to fully justify its request for £655 million. We will consider further information from Thames in relation to our challenges for the final determination.”
Near-real-time microbial monitoring of wastewater discharge and bathing waters is now possible thanks to the BactoSense ID solution created by Swiss-based bNovate Technologies.
Craig Nienaber, Business Development Manager for Safe Access Solutions (SAS) at HUBER Technology, explores why the company is seeing a growing level of interest in its safe access solutions for critical infrastructure providers, including their application in wastewater treatment assets.

Southern Water has released film and images showing what it’s like to walk inside Hampshire’s expanded Yew Hill underground reservoir for the very last time, before it gets filled with water.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.