Severn Trent completes first of three Elan Valley Aqueduct bypass tunnels

Severn Trent has completed the first of three huge multi-million pound bypass tunnels being built to reinforce water supplies for Birmingham.

The Elan Valley Aqueduct (EVA) has been bringing water to the homes and businesses of Birmingham and the surrounding area for over 100 years.  However, after so many years of service, the need for regular maintenance and refurbishment is becoming ever more frequent and so the time has come to provide extra support for the EVA to make sure that it can continue to provide service for another 100 years.  Bring on the Birmingham Resilience Project – Severn Trent’s flagship £300 million programme.

Paul Dennison, programme manager for Severn Trent, explained:

“At the moment, the EVA is the sole source of supply into Birmingham, and storage at our treatment works at Frankley means we can only turn it off for a few days at a time for maintenance.  To allow us to turn it off for longer periods, an alternative water supply for the city is being built.  Work began this month on a new pipeline from Lickhill, near Stourport-on-Severn, 25km into  the existing water treatment works in Birmingham."

“However, our checks on the existing aqueduct show that in three places, there is work that we'd rather do before the new pipeline is completed. As we can’t shut down the aqueduct, we've had to come up with alternative solutions.”

ELAN VALLEY AQUEDUCT WORKThree new tunnels will be built, then connected at either end, to bypass sections of the existing aqueduct.  These will be at Bleddfa, Nantmel and Knighton.  Each of the multi-million pound projects is huge in its own right - the machine used to cut the new tunnels is over 3 metres in diameter.

Paul Denison continued:

“We’ve been working at Bleddfa since October 2015 and a launch ceremony was held in May 2016 to celebrate the arrival and launch of the Tunnel Boring Machine which then spent the next six months underground digging the 1.8km long tunnel.  The machine broke out successfully in December 2016 – right on target, completing the first tunnel."

“The last few weeks have been a busy time for us as we’ve been working on the transfer of flows from the 100 year old aqueduct at Bleddfa into the newly constructed tunnel. We planned the work to coincide with a scheduled shut-down of the EVA, when flow through the aqueduct is suspended for five days to allow inspection and maintenance."

The new tunnel was flooded by removing the barriers from each end, resulting in the flow being shared between the old aqueduct and the new tunnel.  The water was diverted into the new tunnel by placing a series of specially shaped concrete blocks into the aqueduct  gradually turning the flows from the old to the new.

The roof slab sections have now been replaced and Severn Ttrent has begun backfilling the two working areas -  the team completed the flow transfer in just three days. The water company expects everything to be fully back to normal by the end of August at its site at Bleddfa village, and a month later at the site near Monaughty.”

All the tunnelling equipment from Bleddfa has now been transferred to the second site at Nantmel, where the Tunnel Boring Machine is being prepared for its re-launch in April to start work on tunnel number two.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more