NI Water to invest £4.8 million in new Wastewater Treatment Works for Ballyronan

NI Water is scheduled to commence a £4.8 million programme of work this summer to provide Ballyronan with a modern new wastewater treatment facility.

NI_Water_Ballyronan_wastewater_treatment_works_1.jpg

The existing treatment works, which was constructed in the 1970s, will remain in operation while the new infrastructure is being installed at the same site.

Coalisland-based GEDA Construction has been appointed to carry out the 18-month contract which will see the implementation of a temporary working area adjacent to the site to facilitate construction works.

Newry-based Water Solutions Ireland will carry out the extensive mechanical and electrical installation at the site, while Belfast-based RPS Group are providing technical support for the project.

Infrastructure Minister John O’Dowd said:

“NI Water’s substantial £4.8m investment is good news for people who live in the Ballyronan area. The work, which is being undertaken by local companies, will include the installation of state-of-the-art, fully enclosed, treatment tanks, along with advanced electrical and mechanical systems to provide a robust wastewater treatment solution.

“This will support local development and help improve water quality in Lough Neagh delivering economic and environmental benefits for the local community for many years to come.”

NI Water Project Manager, Sean Milligan added:

“Construction work at the site will get underway in full after the July holidays. In advance of that, GEDA will set up their working compound and carry out any necessary preliminary works.

“During the initial construction phase of the project, there will be increased construction traffic at the site and along the Ballyronan Road, as materials and new infrastructure are delivered and excavated spoil removed. There will be less construction traffic during the later mechanical and electrical fit out and commissioning of the plant.”

“This £4.8 million investment is an excellent example of what can be done when the necessary funding is in place.”

NI Water’s capital funding for year 1 of its business plan has already been secured and the business is looking forward to the necessary funding being put in place across the full six-year period to 2027.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more