ENGIE UK and CDPQ to invest up to £1 billion in UK two pumped storage hydro plants in UK

ENGIE UK, part of the France-headquartered ENGIE Group, and its Canadian investment partner CDPQ, are investing up to £1 billion in a refurbishment programme to extend the life of two pumped storage hydro assets in Wales.

PUMPED HYDRO STORAGE DINORWIG POWER STATION WALES

Photo: Dinorwig pumped hydro power station, Wales

ENGIE owns 75% of the plants via First Hydro Company, a 75:25 joint venture with CDPQ. 

The two pumped storage hydro plants at Dinorwig and Ffestiniog are the UK’s leading provider of power storage and flexibility, with 2.1GW of installed capacity.They represent 5% of the UK’s total installed power generation capacity and 74% of the UK’s pumped storage hydro capacity

The preparation of a 10-year project of refurbishment at ENGIE’s Dinorwig pumped storage station has begun, following an 8-year refurbishment at Ffestiniog, enabling the delivery of clean energy whenever needed.

The flexible generation assets, based in North Wales, are essential to the UK Government’s accelerated target of achieving a net zero carbon power grid by 2030. Together they help keep the national electricity system balanced, offering instant system flexibility at short notice.

The plants are now reaching end of life and replanting will ensure clean energy can continue to flow into the next few decades.

Re-planting could see the complete refurbishment of up to all six generating units at Dinorwig – a final investment decision is still to be made on the number of units to replace – while the re-planting at Ffestiniog will be completed at the end of 2025.

The program also involves the replacement of main inlet valves – with full drain down of the stations – and detailed inspections of the water shafts.

Due to the complexity and the scale of engineering involved, and the necessity to keep the plant as available as possible to serve the electricity system, the re-planting project for Dinorwig will take up to ten years, involving specialist technology, bespoke lifting systems, and expert contractors.

Before the main inlet valves can be replaced – preparation which will be completed in 2025 – the plant must be drained down, a slow and careful process which takes two weeks due to the high water pressure levels. The drainage is a rare procedure, typically carried out every 40 years. During this time, engineers will climb inside the water shafts, carrying out a thorough safety and integrity inspection.

The valves themselves, which are amongst the largest valves in existence, were modelled at a reduced scale in a lab and designed as fully working scale models to drive efficiencies. AI was used to optimise and improve the infrastructure and technology. The valves are now waiting to be installed at Dinorwig station, where specialist engineers will lathe and fine tune the seal on site for up to two weeks.

Miya Paolucci, UK CEO, ENGIE, said:

“ENGIE is a key player in the UK’s energy transition and we are making significant financial and resource commitments to reach our decision on whether to invest in the full or partial re-planting of Dinorwig.

“Flexible storage is essential for net zero carbon operation of Britain’s electricity system. It helps balance the system by ensuring there’s always a large volume of “back up” power on standby, that can be delivered in very fast timescales if required. We’re very proud to contribute to the electricity security of supply and green energy ambition of the UK with these extraordinary assets.”

First Minister of Wales, Eluned Morgan commented:

“The renewable energy sector is creating exciting economic opportunities for Wales and is vital in ensuring we meet our future energy targets while reducing our reliance on fossil fuels.

“Investments such as these create high quality jobs for the local community. ENGIE is a longstanding investor in Wales, employing around 200 permanent staff and I’m pleased to support its replanting scheme, which will see the facilities continue to operate for another 25 years.”

Ffestiniog, one of the first pumped hydro-electric systems in the UK, was opened in 1963. As the older of the two plants, refurbishment is already underway, with two units already rebuilt and the last two units set to go live by the end of 2025.

Dinorwig, the largest and fastest-acting pumped storage station in Europe, followed in 1984 and was regarded as one of the world’s most imaginative engineering and environmental projects. At Dinorwig, 2 of the 6 unit Main Inlet Valves were replaced in 2023; with the remaining 4 valves to be installed in 2025. The full replanting to replace up to six pump-turbines and generator-motors (the final investment decision is yet to be taken) will take up to ten years to complete.

Pumped storage hydropower is a key low carbon energy source. At times of high demand, or when the wind isn’t blowing and the sun isn’t shining, and more electricity is required on the national transmission system, the plants release water to generate electricity. At times of low demand, when there is a lot of clean renewable power flowing, the plants pump water back up the mountain, ready for when it’s needed again.

In the first quarter of 2025, ENGIE has acquired a 157 MW portfolio of operating renewables assets in England and Wales, comprising three onshore wind farms and four photovoltaic solar farms. The acquisition also represents an opportunity for ENGIE to deploy battery energy storage systems and solar power plants at the acquired sites, as well as the development of repowering projects, marking a significant step forward in the expansion of its renewable energy development in the UK

France-headquartered ENGIE Group, which is listed on the Paris and Brussels stock exchanges, is a major player in the global energy sector,

In the UK, with 1,300 employees, ENGIE owns and operates a large portfolio of renewable and flexible storage assets, across electrons and molecules, including one of the largest pumped-storage hydro plants in Europe. Its JV company Ocean Winds is one of the largest offshore wind generators in Scotland with 950MW of operating capacity and 882MW in construction.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more