Scottish Power: £400m investment could double Cruachan hydro plant capacity

ScottishPower, the operator of the 440 megawatt (MW) Cruachan Pumped Storage hydro plant near Oban, has completed a two-year feasibility study to determine whether it is possible to expand the station.

The findings show that it would be possible to develop between 400-600 MW additional capacity, with investment of between £300 million to £400 million.

At full operation Cruachan can meet the power demands of more than 200,000 homes. ‎However, unlike other power stations, Cruachan can also act as a ‘battery’. When the turbines are reversed they use excess electricity from the national grid to pump water back in to the upper reservoir, ultimately storing this energy.

Given the increasing importance of renewable energy in Scotland, and the increasing need for energy storage, ScottishPower believes that Cruachan is well placed to help support the grid.

Hugh Finlay, Generation Director at ScottishPower, said: “A new generation of pumped storage hydro would be a major asset for electricity systems worldwide as more renewable electricity continues to come on line. As well as being able to further support peak demand, expanded pumped storage would also be able to effectively store greater levels of electricity at times when renewable energy output is high but demand is low.

“Pumped storage hydro is the most cost effective and well-developed large-scale electricity storage technology in existence. We will now take forward our Cruachan findings with government and regulators.”

ScottishPower will now consider the next steps for the project, including discussions with government on potential support mechanisms.

Cruachan celebrated its 50th anniversary in October 2015. Her Majesty the Queen presided over the official opening ceremony on 15th October 1965, six years after construction had started.

Widely regarded as an engineering masterpiece, and often referred to as The Hollow Mountain, Cruachan was devised by Sir Edward MacColl and was built by a workforce of 4000. Over 220,000 cubic metres of rock was blasted and drilled by explosives experts know as Tunnel Tigers, to create a cavern 1km inside the mountain to house the turbines and a network of pipes and tunnels.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more