Visitors to the Leeds Waterfront Festival this weekend will get the chance to see the innovative technology being used in the £50 million scheme to reduce the risk of flooding to the city.
The Leeds Flood Alleviation Scheme project team will be on hand at the event on Saturday 24 and Sunday 25 June, to explain what work has been done for phase 1 of the scheme in the city centre.
A model of a moveable weir will be demonstrated at the event, which is a replica of those installed in the River Aire at Crown Point next to Knightsway Bridge. The moveable weirs used for the project can be lowered in flood conditions to reduce river levels and the threat of flooding.
The first phase of the Leeds Flood Alleviation Scheme, led by Leeds City Council in partnership with the Environment Agency, aims to reduce the risk of flooding from the River Aire and Hol Beck for residents and businesses in the city centre. The scheme also includes flood risk reduction at Woodlesford.
Rosa Foster, Strategic Partnerships & Projects Manager at the Environment Agency said:
“This event is a great opportunity to demonstrate the moveable weirs before our work in the city centre comes to completion. This is the first time that moveable weirs are being used in the UK for a flood risk reduction scheme.”
Visitors to the event will also get the chance to try out the virtual reality area, and wear headsets to view 360 degree footage from the construction phase of the project and see what it’s like to work inside a cofferdam in the river. A cofferdam is a dry working area created in the river by driving in sheet piling. The last cofferdam is now in place while the final moveable weir is constructed.
The site works for Phase 1 of the Leeds Flood Alleviation scheme, which are being carried out by contractors BAM Nuttall, commenced in January 2015 and are scheduled to be completed this coming September.
It is one of the largest river flood risk reduction schemes in the country which when complete will provide an increased level of protection from flooding from the River Aire and Hol Beck for residents and businesses in the city centre. The scheme also includes defences at Woodlesford.
The project team is currently working on options for Phase 2 of the scheme, which will adopt a catchment-wide approach meaning the entire River Aire catchment area will be considered to help reduce flood risk in Leeds. Consultation on potential options is due to be carried out from September.