Fri, May 08, 2026
Text Size
Thursday, 04 June 2015 06:14

Milford Haven STW - A Wastewater Case Study

Huber Technology recently completed the installation of new escalator inlet screens and screenings handling plant for Welsh Water (DCWW) at Milford Haven STW.

Project Profile

Having completed the installation of escalator screens and screenings handling at Garnswlt STW working direct with DCWW and their South West Capital Delivery team, Huber were asked to look at a similar type of project at Milford Haven STW.   The main difference between the two sites was that the site at Milford Haven  was a raised inlet works and located inside a building.  This  was from the outset of the project a challenge for all involved with the  space available being very  limited and all the equipment supplied would have  to be Ex rated.

Milford Haven - Outside access to site and large door access to Inlet Works

Outside access to site and large door access to Inlet Works

 The existing INKA step screens and Parkwood compactor were close to the end of their asset life. Huber had previously carried out repairs on the inlet screens just 3 months prior to our visit and had warned that spares for both existing screens were getting more difficult to procure. Also, it was noted that the existing screens were struggling to cope with the first flush, which required the local operator to remove large volumes of screenings by hand into a receptacle and dispose into a skip on regular basis and thus becoming  a major health and safety issue. 

Milford Haven - Existing INKA  Parkwood Screens

Existing INKA & Parkwood Screens

 

An initial site survey undertaken by Adrian Heneghan, Huber’s Area Sales Manager, highlighted that this could not be done without some help from a local DCWW contractor. Whitland Engineering were the closest and came recommended by DCWW. Another site visit was made and between Huber and Whitland, scopes of work were agreed and an order was placed on both companies by DCWW to proceed with the project.

Huber Technology supplied:

  • 2 off EscaMax 4000/652/6 Duty/Standby for 400l/s each
  • 1 WAP/L BG4
  • Local Control Panels
  • Local Push Button Stations

Objective

The challenge of getting 2 new escalator screens and a WAP/L compactor into a confined space while keeping the site running was a major feat in itself. Phase 1 of the project was getting the Huber control panels and push button stations delivered 2 weeks prior to the screens. This allowed Whitland Engineering time to get them into position and pre-cabled ready for the new equipment. Phase 2, was for the mechanical installation. The site had upstream storage for 4-5 hours which allowed a reasonable time to remove the old Parkwood compactor and install the new WAP/L BG4 screenings handling unit into a temporary position so as not to hinder the installation of the screens.

Phase 3, with the WAP/L running, one of the INKA step screens was isolated and removed allowing the other to run and keep the plant operational. The new EscaMax was then installed and cabled ready for commissioning. 

                                     Milford Haven - Installation of EscaMax Screen in confined space1Milford Haven - Installation of EscaMax Screen in confined space

Installation of EscaMax Screen in confined space

Phase 4 involved removing the 2nd INKA step screen and installing the other EscaMax unit. Again, once cabled the screen was then ready for commissioning immediately.

                   Milfor Haven - New WAP - L BG4 Screenings Handling Unit 1Milfor Haven - New WAP - L BG4 Screenings Handling Unit 2

New WAP/L BG4 Screenings Handling Unit 

                                 Milford Haven - New EscaMax Screens2Milford Haven - New EscaMax Screens1

New EscaMax Screens

Solution

Throughout all the phases of the project execution,  detailed planning and effective communication between Huber Technology, Whitland Engineering and the DCWW capital delivery team was essential. A collaborative approach and good working relationship between the 3 companies  ensured that this challenging  project was delivered on time and within budget.

David Alford – Contracts Engineer – Huber Technology

“As always with projects having a large amount of site work we encountered a few challenging moments throughout the installation phase but by good communication and working closelywith Whitland Engineering we were able to overcome these with a successful outcome and a satisfied customer.”

Mark James – Milford Haven Site Operator

“Thanks to all involved in getting these screens in and running while keeping the site running. I can now spend more time looking after the rest of the site without having to watch the inlet screens and manually remove screenings. From a health and safety point of view, this is a bonus. The screens and screenings handling are all working really well.”

For more information please contact Rachael Harvey 01249 765000, email This e-mail address is being protected from spambots. You need JavaScript enabled to view it or visit our website www.huber.co.uk

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more