Engineers working on United Utilities’new multi million pound water supplies project for West Cumbria are set to hit a host of new construction landmarks despite coronavirus challenges.

Photo: view along route of new pipeline linking Thirlmere reservoir to West Cumbria, showing the land restored.
July marked the end of a major re-vamp of 23 kilometres of water pipe and the completion of work on a ‘green’ roof at a brand new water treatment works at Williamsgate.
Despite Covid-19 and other challenges, the water company said it is still on track to complete the project on time in 2022.
Now in its third year of construction, the improvement project will ensure there will always be enough water on tap for West Cumbria's households and businesses.
The unique scheme, which will link West Cumbria to the rest of the regional water network, has already achieved a number of significant milestones over the last 12 months including:
- Completion of buildings at a new water treatment works at Williamsgate
- 100km of new water pipes installed to transfer water from Thirlmere to the West Coast via the new Williamsgate works
- Construction of two new pumping stations and two underground service reservoirs
John Hilton, United Utilities’ project director, said:
“This is the first time that we’ve undertaken a project of this scale and we are incredibly proud of our achievements so far.
“Despite many challenges including the Covid-19 outbreak, dry weather, extreme wet weather and flooding, we're still on track to finish in 2022.
“We’re making great progress on the land reinstatement phase for many parts of the project and the longer daylight hours during the summer will mean our teams can work extended hours to get the land returned to normal where we've installed the new pipelines.
“There’s still a lot of work to do but we’re confident that we can maintain progress and continue with the momentum that we’ve built over the last three years on the project.”
During the Covid-19 lockdown the water firm was able to continue construction. At Williamsgate water treatment works the new filtration buildings, storage tanks and offices were finished and construction of the twin aqueducts and new tunnels from Thirlmere Reservoir to Williamsgate was completed.
The green roof at the treatment works is now complete and will provide environmental benefits as well as ensuring that the treatment works blends in to the valley when work is complete.
At High Leys service reservoir, which will store a massive 50 million litres of treated water, the storage tanks and pumping station structure have been completed and tested, and the team is currently working on the electrical installations in the building. Work installing the roof is due to start in August 2020 with landscaping work and seeding taking place during August and September 2020.
Moota Hill service reservoir is smaller than High Leys but still holds 21 million litres of water. Main construction works have now been completed and electrical installation has started. Landscaping work is continuing, with seeding on course to be finished this month. Planting of trees and hedges will begin this autumn and final testing is scheduled to take place during spring 2021.
Between the Lorton Valley and Stainburn two pipelines have been refurbished resulting in the restoration of just over 23km of pipes. The work has been completed through the process of slip lining which involves inserting a smaller diameter pipe inside an existing pipe. It was completed in July 2020 - a year ahead of schedule.
The water mains currently supplies more than 30,000 households and businesses, in towns such as Workington and Cockermouth.
“SAS (Surplus Activated Sludge) is a bit weird and
Owen Mace has taken over as Director of the British Plastics Federation (BPF) Plastic Pipes Group on the retirement of Caroline Ayres. He was previously Standards and Technical Manager for the group.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.