Major works are underway to improve how Southern Water treats wastewater at its Forest Green Wastewater Treatment works.

The £3.1 million construction project, on the Surrey Sussex border near Horsham, will ensure the works can accommodate a growing population in the local area by 2035.
Additional tanks are being added to aid the treatment process, as well as a new stage to remove phosphorus from the final effluent.
Project Manager for Southern Water, Robin Woodward, said:
“We know how important it is to protect and enhance water quality and our precious environment across the areas we serve. These vital improvements at Forest Green Wastewater Treatment Works are much needed in our effort to continually improve the way we treat wastewater.”
Project Manager for contractor GTb, Pat Leonard said the upgrade is one of several projects is working on in the local area.
The work will help Southern Water meet its environmental targets.
Near-real-time microbial monitoring of wastewater discharge and bathing waters is now possible thanks to the BactoSense ID solution created by Swiss-based bNovate Technologies.
Craig Nienaber, Business Development Manager for Safe Access Solutions (SAS) at HUBER Technology, explores why the company is seeing a growing level of interest in its safe access solutions for critical infrastructure providers, including their application in wastewater treatment assets.

Southern Water has released film and images showing what it’s like to walk inside Hampshire’s expanded Yew Hill underground reservoir for the very last time, before it gets filled with water.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.