Severn Trent is beginning a £10 million investment to carry out essential upgrades at its Draycote Reservoir this month.

The project will see Severn Trent making Draycote Water deeper, by working in sections and digging down into the reservoir in the embankments so it can store more water, which will raise the top of the water level on the reservoir slightly.
The innovative project and ways of working means Draycote can be expanded to hold more water, by making the reservoir deeper, not wider – not impacting the shape of the site or local area.
Once complete, Draycote will be able to hold and additional 1.4m cubic meters, around 560 Olympic sized swimming pools, allowing it to meet future water demands.
The circular route around the reservoir closed from 13th October, and work will be carried out in two phases:
- Phase one – around 12 weeks, working on two embankments, Toft Embankment and Farnborough Embankment
- Phase Two – a longer programme of strengthening 4 embankments.
All works are planned to be completed by autumn 2026.
“SAS (Surplus Activated Sludge) is a bit weird and
Owen Mace has taken over as Director of the British Plastics Federation (BPF) Plastic Pipes Group on the retirement of Caroline Ayres. He was previously Standards and Technical Manager for the group.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.