Environment Agency issues environmental permits for new nuclear power station at Sizewell C

The Environment Agency has issued three new environmental permits to NNB Generation Company (Sizewell C) Limited for a new nuclear power station at Sizewell in Suffolk.

Sizewell_C_nuclear_power_station_1.jpg

The permits are required for the station to operate and will allow it to:

  • discharge returned abstracted seawater (from the cooling water system and two fish recovery and returns systems) and other liquid trade effluents (including treated sewage effluent) to the Greater Sizewell Bay – North Sea (water discharge activity permit)
  • dispose of and discharge radioactive waste (radioactive substances activity permit)
  • operate standby power supply systems using diesel generators (combustion activity permit)

 

NNB Generation Company (Sizewell C) Limited applied to the Environment Agency for three environmental permits in May 2020. The Environment Agency consulted on the application from July to October 2020 and on their proposed decision and draft permits from July to September 2022.

Each of the three permits is an important regulatory permission that the company requires to operate Sizewell C nuclear power station. They include the limits and conditions that the company needs to put in place to ensure high standards of environmental protection during commissioning, operation and decommissioning.

The company will need to continue to apply for a range of environmental permits relating to site investigation, construction works and for relevant “associated developments.”

The Environment Agency’s Sizewell C Project Manager, Simon Barlow, said:

“Today’s decision to issue the three permits for these operational activities comes after 10 years of pre-application discussions, three years of technical assessments and two public consultations. In reaching this decision we carefully considered all the responses from a wide range of stakeholders in the local community, national organisations and statutory consultees.

“I would like to thank everyone for contributing their evidence and views and attending our consultation events. We will continue our engagement with the local community as the company moves forward with its plans for construction of the nuclear power station.

“The documents we are publishing today provide detailed explanations of our decisions, show how we have considered all the relevant factors and explain our reasoning. By granting these permits many years ahead of Sizewell C operating, we can positively influence the design, procurement, and commissioning of the power station, whilst also ensuring that people and the environment are protected.”

The Environment Agency is the independent environmental regulator for the nuclear industry in England. The environmental permits issued by the Agency cover site preparation, construction, operation and decommissioning.

The Environment Agency has previously worked with the Office for Nuclear Regulation to carry out Generic Design Assessment (GDA) on the design proposed for Sizewell C, known as EDF-Areva’s UK EPR™. That assessment process ended in December 2012 and the Environment Agency and ONR concluded that the reactor design is ‘acceptable’.

This means that people and the environment will be properly protected if this reactor design is constructed and operated in the UK. This design is currently under construction at Hinkley Point C in Somerset.

The decision documents, a public summary and permits are available on the Environment Agency’s website.

There will be further opportunities to input into the Agency’s decision-making for environmental permits for the Sizewell C site.

News Showcase

Sign up to receive the Waterbriefing newsletter:


Watch

Click here for more...

Login / Register




Forgot login?

New Account Registrations

To register for a new account with Waterbriefing, please contact us via email at waterbriefing@imsbis.org

Existing waterbriefing users - log into the new website using your original username and the new password 'waterbriefing'. You can then change your password once logged in.

Advertise with Waterbriefing

WaterBriefing is the UK’s leading online daily dedicated news and intelligence service for business professionals in the water sector – covering both UK and international issues. Advertise with us for an unrivalled opportunity to place your message in front of key influencers, decision makers and purchasers.

Find out more

About Waterbriefing

Water Briefing is an information service, delivering daily news, company data and product information straight to the desks of purchasers, users and specifiers of equipment and services in the UK water and wastewater industry.


Find out more