UK construction company Osborne and sheet piling sub contractor Suttle Projects recently collaborated on a river bed project to develop an innovative world-first scour protection solution.
The river bed needed to be dug out and replaced at the River Colne, near Staines in Surrey and due to deep, fast flowing water and low headroom of the bridge, traditional sheet piling techniques were not viable.
Osborne worked in partnership with Suttle Projects to overcome the problem by using its bespoke underwater remote control excavator nicknamed 'The Mermaid' for the first time commercially, believed to be the only one of its type to exist globally.
Working underwater brings a number of hazards and challenges – so Osborne worked with Suttle Projects to develop their own innovative solution. The mermaid was deployed, a remote-controlled fully-submersible digger, that scooped out the existing river bed. Divers then set out grout bags – which had to be hand-placed underwater and layered to the right levels. Finally silt could be laid over the top of the hardened grout bags.
In the case of the Staines bridge, the headroom was far too low for a standard mini excavator to be used on a pontoon with an operative sitting in the cabin to work it. In addition, the water was too deep to over pump the channel or divert flow to create a temporary dry work environment.
The mermaid was deployed, situated on a floating pontoon to carry out the scour protection work. Its lower height of 0.8 metres tall versus the standard height of around 2.7 metres meant it was able to work effectively under the bridge, and was safely activated a few metres away by an operative managing the remote control unit.
The mermaid took 18 months to build in-house by converting a conventional mini excavator, removing the cabin and engine and adding remote controls at an overall project cost of £65,000. The remote control unit was connected via hydraulic umbilical leads, supplying the machine with hydraulic power. It works on a hydraulic pressure of around 150 bar, with a flow rate of 25-50 litres per minute, weighing 4 tonnes.
Paul Fagan, Osborne Site Manager, said:
“The use of this self-developed technology simplified a complex operation, significantly reducing the time divers had to spend in the water. We are delighted with the outcome of this project and always look to new technology and better ways to deliver results.”
Director of Suttle Projects, Joe Paine, explained that a previous scour protection project with extremely heavy rainfall and a very low railway bridge, had needed divers to place concrete and excavation with a type of venturi water suction pipe, suspended from a pontoon. The solution was both time consuming and costly. He added:
“ We soon realised that a conventional small excavator that was able to work freely under water would provide the ideal, innovative solution. We could find nothing of this type on the market globally, so with support from Ross Welsh at Pirtek Poole, who specialise in fluid transfer solutions, we decided to build our own machine.
“By collaborating with Osborne to use this equipment in the project, we were able to provide an efficient and cost-effective solution for what was historically a complicated and expensive task.'
The mermaid, which is now available for hire by other companies, is currently set up to work underwater up to 25m deep, but can easily be set up for deeper water conditions if required.
HUBER Technology UK & Ireland are inviting people to register for their March webinar where they will be providing information about HUBER water intake screens for municipal and industrial applications.

Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.