The Environment Agency and a wide range of partners have completed the Outstrays Managed Realignment Scheme, creating 250ha of intertidal habitat by embankment realignment at a total cost of £56.3 million.
The Agency has invested £35.5 million delivering the improved flood defences, new habitat and improved public access, with an additional contribution of £9.8 million from ABP. A further £11 million is being invested in two new pumping stations (to be completed by 2027).

Photo: View of the new embankment with intertidal habitat in the background
The Outstrays Managed Realignment Scheme (OMRS) at the Humber Estuary in Yorkshire has been delivered by the Environment Agency in collaboration with Associated British Ports (ABP), working together with many other organisations.
The project has been designed and built by contractor JBA Bentley. Further to the successful delivery of the managed realignment scheme, the company has been awarded the upgrade of the adjacent Skeffling and Winestead pumping stations.
Nick Lister, Director at JBA Bentley, said:
“JBA Bentley are proud to have collaborated closely with two of our key clients - the Environment Agency and Associated British Ports - to deliver this important managed realignment scheme at The Outstrays.
“As a fully integrated design-and-build business, our engineering, environmental, and construction teams worked with a range of partners and stakeholders to provide the detailed design and implementation of more than 175ha of intertidal habitat and supporting freshwater grassland.
“This flagship project - which will ensure that the unique environment of the Humber Estuary is preserved for future generations - has provided great opportunities for social value, carbon reduction and innovative flood embankment construction.”
The vast new 250-hectare area of habitat consists of 175 hectares is intertidal habitat (saltmarsh and mudflats) and 75 hectares is terrestrial freshwater ‘wet grassland’.
Much of the new habitat is compensatory habitat. Its creation replaces important intertidal habitat lost as a result of flood risk management work and port development in other parts of the estuary.
Strategically, OMRS has enabled improvements to tidal defences that benefit more than 100,000 people, industry and infrastructure around the estuary, including in Hull, Hessle, South Ferriby and Stallingborough. It will also facilitate future port expansion by ABP.
The two new pumping stations will be completed in 2026 and 2027, replacing older ones at Skeffling and Winestead Outstrays. Their increased capacities and carbon efficiency will make an important contribution to the management of flood risk for local residents, businesses and farmland.
New intertidal habitat created by new 5.5km flood embankment
The new intertidal habitat at Outstrays has been created by building a state-of-the-art new 5.5km flood embankment and creating a breach in the old defence that allows the tide to flow in and out of the ‘basin’ created in between. The new embankment helps reduce flood risk to property and farmland in South Holderness.
The scheme has also created other new habitats, including the wet grassland, new hedgerows and tree planting as well as preserving dune habitat. These all complement the intertidal areas, increasing biodiversity.
Environment Agency Chair, Alan Lovell, said:
“We know the devastating impact that flooding can have, which is why protecting people and communities is our top priority.
“The delivery of the Outstrays Managed Realignment Scheme is a significant milestone, enabling both the creation of major flood defences in Humberside and providing vital wetland habitat for migratory birds.
“Without this project, our vital ongoing investment to reduce tidal flood risk to the homes, businesses and industry across the Humber could not happen, demonstrating the power of engineering and nature working hand-in-hand.”
The Environment Agency’s Humber Strategic Manager, Helen Todd, said the project and the learning from it are contributing towards the longer-term goals of managing tidal flood risk as part of Humber 2100+, which will set the way forward in adapting to sea level rise for the next 100 years.
Andrew Dawes, Regional Director of Associated British Port (Humber) commented:
“This scheme represents a major milestone, not just in terms of engineering and environmental achievement, but in what it means for the future of the Humber region...
“Developing new estuarine habitat like this is a crucial way of ensuring that potential environmental impacts from the development of future port infrastructure can be offset and, consequently, this project is a powerful example of how infrastructure and nature can work hand in hand.
“It supports the Humber’s role as the UK’s gateway for trade, while also enhancing flood resilience and we already have nationally significant projects in development, ready to start construction, that are linked to the site.”
“SAS (Surplus Activated Sludge) is a bit weird and
Owen Mace has taken over as Director of the British Plastics Federation (BPF) Plastic Pipes Group on the retirement of Caroline Ayres. He was previously Standards and Technical Manager for the group.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.